A window schedule lists every window and external door on a building, one row per opening, with the information a manufacturer needs to price and make it. A complete schedule gets a complete quote back. A schedule with gaps gets a quote full of assumptions, or a string of questions before anyone can price it. This guide covers what a schedule is for, the columns it needs, how to mark the compliance requirements, and the mistakes that slow a quote down.
What a Window Schedule Is For
The schedule is the single source of truth for the openings in a building. The draftsperson or architect sets the sizes and styles on it, the engineer sizes lintels around it, the carpenter frames to it, and the window supplier quotes and manufactures from it. That is why the schedule matters more than any single drawing: it is the document every trade refers back to.
For a quote, the schedule does three jobs. It tells us how many units there are and what each one is. It tells us what each unit has to achieve, from the BASIX glazing commitments to the BAL and acoustic requirements. And it gives every unit a mark, so the quote, the order, the delivery and the installation all refer to the same opening.
The Columns Every Schedule Needs
Most schedules come out of the drafting software already, but they often leave out the columns a window supplier needs. These are the ones that let us price accurately the first time:
| Column | Example | Why we need it |
|---|---|---|
| Mark | W01, W02, D01 | The label on the plan, so every unit traces back to one opening |
| Room and elevation | Bed 2, north | Tells us orientation, privacy and which reports apply |
| Width x height (mm) | 1200 x 1500 | Overall frame size; final sizes are measured on the built frame |
| Style | Awning, tilt and turn, sliding door | The opening type for each unit |
| Opening direction | Hinged left, slides right | Viewed from outside, so nothing is made the wrong hand |
| Glazing | Double glazed Low-E, obscure | From the BASIX certificate and any privacy needs |
| BAL | BAL-29 | From the bushfire assessment, per elevation |
| Acoustic | Laminated 10.38 / 12 / 6 | Only where an acoustic report sets a build-up |
| Colour and hardware | Black outside, white inside | Finish and handle colour |
| Screens | Flyscreen, BAL screen | Insect or bushfire screens where needed |
| Notes | Restrictor, safety glass | Window safety devices, toughened glass zones, anything unusual |
Here is what a few rows look like when they are filled in properly:
| Mark | Room / elevation | W x H (mm) | Style | Glazing | BAL | Notes |
|---|---|---|---|---|---|---|
| W01 | Kitchen / east | 1800 x 900 | Awning (2 sash) | Double glazed Low-E | BAL-19 | |
| W02 | Bed 2 / north | 1200 x 1500 | Tilt and turn | Double glazed Low-E | BAL-19 | Window safety device |
| W03 | Ensuite / west | 600 x 900 | Awning | Double glazed, obscure | BAL-19 | Toughened |
| D01 | Living / north | 3600 x 2400 | Sliding door (3 panel) | Acoustic laminated | BAL-19 | Per acoustic report |
Example only: the glazing, BAL and acoustic entries come from your own BASIX certificate, bushfire assessment and acoustic report.
Marking Glazing, BAL and Acoustic Requirements
Three documents usually set the glass before anyone chooses a colour, and the schedule should carry what each one says.
- BASIX. Every new home in NSW needs a BASIX certificate, and it lists the windows and glazed doors with their sizes, frame type and glazing type. Copy the glazing type for each opening into the schedule, because what is installed has to match the certificate.
- BAL. On bushfire prone land the bushfire assessment sets a BAL for each elevation, and it decides the glass, the seals and any screens. Mark the BAL against every opening on that elevation, not once at the top of the page.
- Acoustic. Near main roads, rail lines and flight paths an acoustic report may set a glazing build-up per elevation or per room. Copy the build-up exactly as the report states it.
Two more notes save a lot of back and forth: mark the openings that need safety glass, such as glass near doors, bathrooms and low sills, and mark bedroom windows that need a window safety device to restrict the opening.
Common Mistakes That Slow a Quote
- Sizes without a mark. Without W01, W02, the quote cannot be matched back to the plan, so every query takes twice as long.
- Opening direction left off. A hinged window or door made the wrong hand is a remake. Always state the hinge side, viewed from outside.
- BAL on the cover sheet only. The BAL often differs by elevation. Put it on every row.
- Acoustic build-up paraphrased. Copy the report's build-up exactly; laminated glass of a different thickness is a different product.
- No lock-up date. The lead time is worked back from the date the building needs to be closed. Without it, nobody can confirm the programme.
- Supply only or supply and install not stated. The two prices describe different jobs and cannot be compared.
Send Us Your Schedule
Send the schedule with the elevations, the BASIX certificate, the bushfire assessment if there is one, any acoustic report, your target lock-up date, and whether you want supply only or supply and install. We price every opening from it and come back with an itemised quote.
If you build regularly, our page for builders and developers explains how we work with trade customers. Building your own home? See new home windows for how we quote a whole house.
Frequently Asked Questions
What is a window schedule?
A window schedule is a table that lists every window and external door on a building, one row per opening, with its mark, size, style, opening direction and glazing. Trades and suppliers use it to frame, price and manufacture the openings.
Who prepares the window schedule?
Usually the architect or draftsperson, as part of the plan set. Builders and owner builders often add the glazing, BAL and acoustic details from the reports before sending it for quotes.
Are the sizes on the schedule the final sizes?
No. The schedule sizes are used to quote, but the units are manufactured to sizes measured on the built frame, because built openings are never exactly the drawn size.
Do I need to put the BASIX glazing on the schedule?
Yes. The windows installed have to match the glazing types on the BASIX certificate, so copying them into the schedule makes sure the quote prices the right glass.
Can you quote without a schedule?
We can quote from the plans and elevations, but a schedule is faster and more accurate. Our free template is a quick way to put one together.